Brandon Boulevard's Tunnel Is Finished. Moon Avenue's Work Runs Into 2027.

If the crews have finished tunneling under Brandon Boulevard, why is North Moon Avenue still fenced off?

The South Hillsborough Pipeline goes under Brandon's busiest road and through the side streets around it. In early October, Tampa Bay Water's project team reported that the microtunnel beneath Brandon Boulevard at North and South Moon avenues was complete and that restoration had started. That was the hardest crossing on this stretch. It is also the only one that went underground. The streets on either side are being opened up from the surface, one block at a time, and that work will shape errands around Moon Avenue and Robertson Street through the holidays and well past them.

A tunnel under the boulevard, trenches everywhere else

The pipeline is a drinking-water transmission line. It is 26 miles long and up to five feet across. It starts at Tampa Bay Water's regional surface water treatment plant in Brandon, connects to Hillsborough County's Lithia Water Treatment Plant, and ends at a new county connection at Balm Riverview and Balm roads. When it is finished, it will carry up to 65 million more gallons of water a day to the county's southern service area.

According to the project fact sheet, the route has 17 tunnel locations, used to limit disruption at major roadways and waterways. About 24 of the 26 miles are being laid by open trench. That ratio explains this fall's work in central Brandon. Brandon Boulevard is one of the roads the project tunneled under so traffic could keep moving. The neighborhood streets the line follows to reach that crossing are trench work.

In Brandon, the published route runs east from the Falkenburg Road crossing at Woodberry, past Providence to Limona. From there it follows Victoria Street, North Moon Avenue, West Robertson Street and Parsons Avenue past Lumsden, then John Moore Road, Ronele Drive, South Kings Avenue and Alafia Boulevard. The tunnel under Brandon Boulevard ties the North Moon section to the South Moon section.

Where each Brandon segment stands in early November

Here is each segment with its most recent scheduled status. The project marks every date as subject to change.

Street segment Latest scheduled status
Brandon Blvd at North and South Moon Microtunnel complete; restoration underway as of Oct. 9
North and South Moon access Scheduled to be restored by early November, weather permitting
North Moon Ave, Victoria St to Brandon Blvd Open-trench installation expected through late December
South Moon Ave Not scheduled to begin until late 2027
Ronele Dr west of El Greco Partial restoration scheduled the week of Oct. 26
South Kings Ave southbound, Ronele to Dali Outside lane reopened Oct. 7; median restoration at a later date
Falkenburg Rd north of Woodberry Outside northbound lane closed Oct. 26 for up to one week

"Early November" in the second row is a target, and it carries a weather caveat. Restored access also does not mean the work is finished. The same October 9 update said open-trench installation would keep going on North Moon through late December. For the actual status on any given morning, check the project's Detours and Alerts page, which posts closures as they are scheduled.

Two of the other segments are close to finished. In early October, crews reopened the southbound outside lane of South Kings Avenue, from just south of Ronele Drive to Dali Drive, after repairing a bridge barrier. The median restoration there was pushed to a later date that has not been announced. In late September, Ronele Drive was closed to through traffic while trenching moved east toward John Moore Road, and that work was expected to take about two months. The current schedule lists partial restoration on Ronele west of El Greco starting the week of Oct. 26.

The Falkenburg closure, which took the outside northbound lane from south of the CSX Railroad to about 300 feet north of Woodberry Road, began Oct. 26 and was scheduled to last up to a week. The project said businesses on the east side of Falkenburg would remain accessible during the closure.

North Moon through December

North Moon Avenue is the segment most likely to affect holiday errands. The closure that started Oct. 5 shut the stretch between Victoria Street and Brandon Boulevard to through traffic and to pedestrians, and both sidewalks closed. Local access stayed open. The posted detour for drivers runs:

  1. North Knights Avenue
  2. Victoria Street
  3. North Parsons Avenue
  4. Brandon Boulevard

The project said local access would shift as the work moved along and that crews would keep homes and businesses reachable. Normal construction hours on the pipeline are 7 a.m. to 6 p.m., Monday through Saturday, with occasional night work. That means Saturday errands near Moon and Victoria will usually overlap with active crews. Sunday is the one day the standard schedule leaves out.

The shops inside the work zone

The project team has twice featured businesses near the Brandon Boulevard crossing that stayed open during construction. Most are on the short blocks of West Brandon Boulevard, Robertson Street and Moon Avenue, right next to the tunnel site.

On West Brandon Boulevard, the project's September roundup named:

  • Brandon Meats and Market, 247 W. Brandon Blvd., which sells fresh meats, produce, cheeses and coffee, with weekly specials that include seafood, deli and Latin foods
  • Value Pawn and Jewelry, 209 W. Brandon Blvd.
  • Black Label Tattoo, 216 W. Brandon Blvd., which has done custom work since 2014 and takes walk-ins

A block away, the same roundup named A New You Pink Boutique at 106 W. Robertson St., a women-focused boutique in Brandon since 2011, and Parker Pawn at 127 S. Moon Ave.

The October 9 update added three more:

  • Nothing Like Us Detailing, set up just outside the Parker Pawn parking lot, which offers washes and full interior and exterior detailing
  • Arnold Dentistry, 257 W. Brandon Blvd., which has served Brandon for nearly 30 years
  • Brandon Medical Center, 122 S. Moon Ave.

Two of those addresses are on South Moon Avenue, the segment set for its own open-trench work in late 2027. Once the early-November access target is met, South Moon should have a quieter stretch until then. North Moon stays active through December. The project put it this way in its October update: "with the holiday season approaching, your continued support goes a long way." Its Shop Local directory lists more businesses along the whole corridor.

A second project on the same boulevard

The pipeline is not the only work on Brandon Boulevard this fall. Farther east, the Florida Department of Transportation is repaving SR 60 from Buckingham Place to Lithia Pinecrest Road. The $3.7 million project covers just under a mile and is being built by Hubbard Construction Company. Along with new pavement, it changes some turning movements, repairs damaged sidewalk and adds pedestrian lighting at an intersection.

That project started March 13, 2026, and FDOT expects it to finish in fall 2026. Lane closures are limited to 9 p.m. to 6 a.m. each night, and driveways, sidewalks and side streets stay open. The two projects run on different schedules. The pipeline blocks around Moon Avenue are worked during the day, six days a week. The SR 60 lane closures to the east happen overnight, and that project is close to done.

Why the Moon Avenue blocks will see more of this

The schedule beyond this year explains why central Brandon will keep seeing crews. The project's schedule page lists construction from fall 2025 through 2028, the pipeline in service at the end of 2028, and restoration in the first half of 2029. The January 2026 fact sheet lists late 2028 for service and summer 2029 for completed construction. Read together, the line should carry water before the last surface repairs are done.

The pipeline is estimated to cost $505.7 million. Hillsborough County is funding up to $84 million. The Southwest Florida Water Management District has prioritized $145 million in co-funding, and the state has added a $2.9 million grant. The 26-mile route reaches well past Brandon. On the same schedule page that lists the Moon Avenue work, crews are also on Boyette Road, near the FishHawk Sports Complex, and at 4142 Alafia Blvd.

For the blocks around Moon Avenue, that adds up to a sequence. North Moon is trenched through December. South Moon is planned for late 2027. Restoration along the route continues into 2029. The project lists email alerts, door hangers, yard signs and variable message boards as its advance-notice tools, and it posts updates on Tampa Bay Water's Nextdoor and Facebook pages.

If you own a home near Moon Avenue, Victoria Street or Ronele Drive and want to know how a multi-year construction schedule might affect when you list, the Kat White Team can walk through the timing with you and prepare a current value for your property. Request Your Home Valuation to start that conversation.